CXMT Shanghai (Pudong DRAM ‘Super Factory’) · 长鑫存储上海基地

ChangXin Memory Technologies (CXMT) | Memory

A genuinely new DRAM mega-fab, separate from CXMT’s Hefei headquarters site, entering substantive construction in March 2026 — this tracker did not capture…
Published

October 11, 2026

TipWhy This Matters

A genuinely new DRAM mega-fab, separate from CXMT’s Hefei headquarters site, entering substantive construction in March 2026 — this tracker did not capture it in an earlier pass, and it is one of the single largest individual under-construction projects in this entire dataset. Planned monthly capacity of 400,000-600,000 wafers would be 2-3x CXMT’s existing Hefei output.

Chinese name: 长鑫存储上海基地 (Chángxīn Cúnchǔ Shànghǎi Jīdì)

What does this facility make?

High-end DDR5 and LPDDR5X DRAM, plus a dedicated HBM3 line (50,000 wafers/month of the planned total) aimed at AI compute, server, and automotive-grade demand.

Why does it matter?

If completed on the stated schedule, this single fab would roughly double CXMT’s total DRAM capacity and push the company further up the global DRAM ranking — concrete evidence that the ‘many fabs under construction’ reality in China is larger than a facility-by-facility reading of status fields that lag real-time news can capture without active, repeated rechecking.

Key Facts

Company ChangXin Memory Technologies (CXMT)
Type Memory
Category State-Backed
Capability 12-inch (300mm) DRAM wafer fab — DDR5, LPDDR5X, and HBM3
Status Under Construction
Capacity Not yet recorded
Investment ¥345亿元
Funding Source Local Govt
Location Shanghai, Shanghai Municipality
Current Node Not yet researched
Entity List No
Equipment Origin Not yet assessed
Last Verified Not recorded (newest source dated Sep 2026)

Technical Complexity

4.4/5

Technology Node Trajectory

Node history not yet researched.

Project Timeline

  • Mar 2026 — Project enters substantive construction progress
  • Sep 2026 — CXMT announces it will deploy ¥18 billion of IPO over-subscription proceeds toward DRAM R&D and a Phase 2 back-end (wafer test) base, part of a combined ¥34.9 billion in related investment

Sources