Each row represents a facility. Bars show the span from construction start (or announcement, if construction hasn’t begun) to expected or actual completion. For cancelled projects, the bar is faded and ends at the last recorded event (abandonment, takeover, or bankruptcy), not today. Diamond markers (◆) mark the announcement date. The dashed line marks today.

Recent Milestones

  • Dec 2027 — Target date for the Xiqing fab to reach full planned capacity (100,000 wafers/month) (SMIC Tianjin (Xiqing))
  • Nov 2026 — Tom’s Hardware’s 2026 memory-industry survey lists the Shanghai fab as under construction, tools 2H 2026, volume 2027 (CXMT Shanghai (Pudong DRAM ‘Super Factory’))
  • Nov 2026 — Announces ¥9.1 billion capital increase into Phase 4 vehicle 晶奕集成 (Nexchip ¥5.1bn, Hefei Construction Investment ¥3bn, Huaqin-backed Hefei Qinhe ¥1bn); Nexchip’s stake falls to 63.96%; subject to shareholder approval (Nexchip Hefei)
  • Nov 2026 — Reuters reports, citing an internal notice, that YMTC has put the IPO’s strategic placement on hold amid weak markets; listing could slip to H1 2027. The application remains at the SSE inquiry stage (YMTC Wuhan)
  • Sep 2026 — Board approves ¥18 billion of IPO over-subscription proceeds for two Hefei projects: a ¥24.1 billion DRAM technology R&D project at the Xinqiao 12-inch base and a ¥10.8 billion Phase 2 wafer back-end test base (¥34.9 billion combined); still subject to shareholder approval (CXMT Hefei)
  • Sep 2026 — Breaks ground on the SiEn Industry Innovation Center, a five-building R&D complex (not a new fab line) in the Qingdao Free Trade Zone IC industrial park (SiEn Qingdao)
  • Sep 2026 — Fifth-generation (G5) DRAM platform declared in production — ~12nm-class half-pitch on ArF immersion multi-patterning — followed by an October 2026 statement that G5/LPDDR6 are in mass production (CXMT Hefei)
  • Sep 2026 — Reuters, via Chinese reprints, reports CXMT is preparing to enter NAND flash with an R&D pilot line inside the planned Beijing fab (CXMT Hefei)
  • Sep 2026 — Share transfer completed — Fab 5 becomes wholly within the listed Hua Hong company (HLMC (Shanghai Huali, Fab 5 & Fab 6))
  • Sep 2026 — Hua Hong Semiconductor formally announces the Wuxi Phase 3 joint venture: US$6.95 billion total (US$4.17B equity, US$2.78B debt), group share about US$2.127 billion, 55,000 wafers/month (Hua Hong Wuxi (Fab9, Phase II))