SMIC Tianjin (Xiqing) · 中芯西青
SMIC | Fab
SMIC’s fourth major mature-node fab of this expansion wave (中芯西青, 100% SMIC-owned), located in Tianjin’s Xiqing Development Area.
TipWhy This Matters
SMIC’s fourth major mature-node fab of this expansion wave (中芯西青, 100% SMIC-owned), located in Tianjin’s Xiqing Development Area.
Chinese name: 中芯西青 (Zhōngxīn Xīqīng)
What does this facility make?
12-inch (300mm) wafers spanning 0.18 micron to 28nm process nodes.
Why does it matter?
Extends SMIC’s mature-node capacity — the segment least affected by advanced-lithography export controls — into a fourth Chinese municipality. Domestic trade coverage in early 2025 described all four of SMIC’s 2020-2022-era mega-fab JVs (Lingang, Jingcheng, Xiqing, Shenzhen) as having begun reaching production in stages (‘陆续达产’) by that point, with Xiqing’s full-capacity ramp (达产) targeted for end of 2027.
Key Facts
| Company | SMIC |
| Type | Fab |
| Category | State-Backed |
| Capability | 12-inch (300mm) wafer foundry, 0.18 micron to 28nm |
| Status | Operational |
| Capacity | Planned: 100,000 wafers/month (300mm), as of 2022-08 — planned per framework agreement (28–180nm); not installed |
| Investment | $7,500M |
| Funding Source | Local Govt |
| Location | Tianjin, Tianjin Municipality |
| Current Node | Not yet researched |
| Entity List | Yes — US Commerce BIS (18 Dec 2020) |
| Equipment Origin | Not yet assessed |
| Last Verified | Not recorded (newest source dated Sep 2026) |
Technical Complexity
3.4/5
Technology Node Trajectory
Node history not yet researched.
Project Timeline
- Aug 2022 — SMIC signs framework agreement to invest $7.5 billion in a new 12-inch fab in Tianjin’s Xiqing district, initial registered capital $5 billion
- Sep 2022 — Construction begins on the Tianjin Xiqing fab
- Jan 2023 — Earliest reported production start for the Xiqing fab, per Chinese industry trade coverage
- Dec 2027 — Target date for the Xiqing fab to reach full planned capacity (100,000 wafers/month)
Sources
- Chinese chip maker SMIC boosts expansion with US$7.5 billion investment in new Tianjin plant amid concerns of US sanctions (26 Aug 2022)
- China’s biggest chip maker SMIC pushes ahead with construction of new Tianjin plant despite Covid-19 lockdowns (01 Sep 2022)
- 中芯国际75亿美元项目落地,解读背后的西青’芯’速度 (EEFocus) (28 Sep 2026)
- 国内四条12英寸晶圆生产线投产! (Sina Finance) (06 Jan 2025)
- 中芯国际关于签订合作框架协议的公告 (天津西青) (27 Aug 2022)