HSMC Wuhan (Hongxin Semiconductor — cancelled) · 武汉弘芯半导体制造有限公司

Wuhan Hongxin Semiconductor Manufacturing Co. (HSMC) | Fab

The emblematic China fab-boom failure and this tracker’s first explicit Cancelled entry.
Published

November 27, 2026

TipWhy This Matters

The emblematic China fab-boom failure and this tracker’s first explicit Cancelled entry. A ¥128 billion ‘14nm/7nm’ project (Wuhan’s 2020 major-project list: ¥52 billion phase 1, ¥76 billion phase 2), 90%-owned by a shell (北京光量蓝图) that paid in nothing of its ¥2 billion registered capital. It had spent ¥15.3 billion by end-2019, took delivery of a new, unused ASML TWINSCAN NXT:1980Di DUV scanner (repeatedly misreported in Chinese media as ‘the only 7nm-capable tool in China’), and mortgaged it for about ¥580 million to Wuhan Rural Commercial Bank.

Chinese name: 武汉弘芯半导体制造有限公司 (Wǔhàn Hóngxīn Bàndǎotǐ)

What does this facility make?

Nothing: unfinished shells. Dongxihu district state vehicles took over the shareholding from late 2020, and on 26 February 2021 management told all roughly 240 staff that there was no plan to resume work.

Why does it matter?

HSMC’s collapse, flagged publicly by the Dongxihu district government’s own 30 July 2020 report (later deleted), fed the 2020-21 central-level push against rogue semiconductor pledges and the debate over local-government fab financing. Site reuse as of 2025-26 is not verified. Keeping cancelled projects in the tracker matters: the denominator of announced Chinese fabs is as analytically important as the operational numerator.

Key Facts

Company Wuhan Hongxin Semiconductor Manufacturing Co. (HSMC)
Type Fab
Category Private
Capability Never produced — planned 14nm/7nm logic fab + advanced packaging (claimed ~¥128B); ~300 of 3,560 planned tools ever received
Status Cancelled
Capacity Not yet recorded
Investment Not disclosed
Funding Source Local Govt
Location Wuhan, Hubei
Current Node Not yet researched
Entity List No
Equipment Origin Not yet assessed
Last Verified 27 Nov 2026

Technical Complexity

4.4/5

Technology Node Trajectory

Node history not yet researched.

Project Timeline

  • Nov 2017 — Registered in Wuhan Linkonggang (Dongxihu) with a claimed ¥128B plan (14nm phase 1, 7nm phase 2, 30,000 wafers/month each)
  • Dec 2019 — ASML NXT:1980Di DUV tool arrives — the only major tool ever delivered
  • Jul 2020 — Dongxihu district government’s H1 economic report warns of a large funding gap and risk of the project stalling
  • Nov 2020 — Dongxihu district state vehicles take over HSMC’s controlling shareholding
  • Feb 2021 — Staff told there is no plan to resume work; all employees asked to resign by 5 March 2021

Sources


NoteHave an update about this project?

Spotted something wrong or out of date? Suggest a correction for HSMC Wuhan (Hongxin Semiconductor — cancelled) (opens a short GitHub form; pick this facility from the list). Chinese-language sources and exchange filings are welcome.