SMIC Tianjin (former Motorola 8-inch) · 中芯国际集成电路制造(天津)有限公司
SMIC | Fab
SMIC acquired Motorola’s Tianjin fab in 2003 (entity registered 3 November 2003) — one of the earliest foreign fab assets absorbed into China’s domestic fo…
TipWhy This Matters
SMIC acquired Motorola’s Tianjin fab in 2003 (entity registered 3 November 2003) — one of the earliest foreign fab assets absorbed into China’s domestic foundry base, and the mature-node counterpart to the new 中芯西青 12-inch JV in the same municipality.
Chinese name: 中芯国际集成电路制造(天津)有限公司 (Zhōngxīn Tiānjīn)
What does this facility make?
200mm mature logic/power wafers, 0.35µm–90nm, incl. the 2018 Phase-2 capacity expansion.
Why does it matter?
Together with Zhangjiang S1 and Shenzhen’s 8-inch line (Dec 2014), this is the SMIC legacy-8-inch layer the tracker had entirely missed — a reminder that China’s wafer capacity sits at least as much in 20-year-old fabs as in the headline mega-JVs.
Key Facts
| Company | SMIC |
| Type | Fab |
| Category | State-Backed |
| Capability | 8-inch (200mm) wafer fab — 0.35µm–90nm; installed ~45,000 wafers/month after Phase-2 expansion, ~60,000 reported at full ramp |
| Status | Operational |
| Capacity | Not yet recorded |
| Investment | Not disclosed |
| Funding Source | Local Govt |
| Location | Tianjin, Tianjin Municipality |
| Current Node | Not yet researched |
| Entity List | Yes — US Commerce BIS (18 Dec 2020) |
| Equipment Origin | Not yet assessed |
| Last Verified | Not recorded (newest source dated Oct 2026) |
Technical Complexity
2/5
Technology Node Trajectory
Node history not yet researched.
Project Timeline
- Nov 2003 — Entity established on the acquired former Motorola Tianjin fab
- Jul 2018 — Phase-2 expansion first new process equipment moves in (45k→60k wafers/month)
Sources
- 中芯天津:2003年收购摩托罗拉天津厂沿革 (东吴证券研报) (03 Sep 2025)
- 中芯国际集成电路制造(天津)有限公司工商信息 (企查查) (01 Oct 2026)